The following figure shows an example of cross probing between the Timing Summary report and the Device window. The following steps take place in this Non-Project Mode example:
- Vivado IDE opens a post-route design checkpoint.
- The Timing Summary report is generated and opened using
report_timing_summary -name. - The Routing Resources are enabled in the Device window.
- When you select the timing path in the Timing Summary report, cross probing on the path occurs automatically in the Device window. See the following figure.
Figure 1. Cross-Probing Between Timing Report and Device Window
For more information on analyzing reports and strategies for design closure, see the Vivado Design Suite User Guide: Design Analysis and Closure Techniques (UG906).